The following photos were taken August 5 when the Board met with the construction team.
Much of the heavy work on D & E is complete. Painters are in the process of caulking and putting the final coat on D & E. Deck railing steel work is complete on D & E, and the steel fabricator is finishing up the custom railings for the D/E courtyard.
The framing crews have been busy on A/B/C and making good progress. C building windows, siding and decks are nearly complete with some steel remaining. Newels and windows are going in on B, and have started on A in parallel.
The entrances on east and west side of D & E, and west side of B & C are nearly complete except for some minor electrical, stone work, flat work, roofing, and painting. The entrance on the east end of A & B is ready for framing. The footings have been poured and backfilled. The final shipment of timbers for the east A/B entrance should arrive any day now, and soon we will see that entrance built.
The stone mason has made some excellent progress. There are some photos of the new stone work. As the project has come together, we have also made some minor additions in stone work that we feel will enhance the overall finished look.
The pace has really picked up and Travis is confident that they will meet our construction deadline.

D Building - August 5 (above)

C-Building August 5 (above)

B-Building from Four O'Clock Road.

Entry west end of D/E. Also new stone work on west end of D.
Concrete pillars and retaining wall to have stone added.

B/C Entrance

Courtyard stone work on C-building, August 5. Some trim / cap stone still to be added